Backlog and dependency register

Status legend: Done, Manual pending. The repository board uses a one-item work-in-progress limit; this snapshot is the portable source for the final evidence submission.

ID Deliverable Depends on Milestone Status Acceptance evidence
P01 Repository, Vite project and quality scripts M1 Done package.json, clean quality gate
P02 Requirements, journeys and acceptance criteria P01 M1 Done overview.md
P03 Types, validation, versioned storage and sample data P01 M2 Done storage/domain tests
P04 App shell, design tokens and responsive layout P02 M2 Done viewport captures
P05 Goal list and CRUD P03, P04 M3 Done component and E2E tests
P06 Task CRUD, status, priority and due dates P05 M3 Done component and E2E tests
P07 Dashboard, progress and upcoming tasks P06 M4 Done dashboard capture
P08 Search, filtering and sorting P06 M4 Done component and E2E tests
P09 Export/import, sample reset and recovery P03, P06 M4 Done storage tests and UI
P10 Keyboard, semantic controls, errors and empty states P07P09 M4 Done manual code/UI review
P11 Unit, component and core browser suites P03P10 M5 Done 9 unit/component + browser suite
P12 Required responsive pass and fixes P10, P11 M5 Done before/after 1680 evidence
P13a Google Chrome, Chromium and Firefox test pass P12 M5 Done automated browser results
P13b Microsoft Edge manual pass P12 M5 Manual pending Windows Edge checklist
P13c Two physical-device sessions P12 M5 Manual pending signed device records/screenshots
P14 Evidence documents and release package P13a M6 Done with appendable placeholders DOCX/PDF outputs

Board snapshot

Backlog Ready In progress Review/Test Done
P13b Edge session; P13c device sessions Replace pending appendix evidence after sessions P01P12, P13a, P14

The manual items are intentionally not reported as complete. Their result may change the browser/device competency outcomes and must be incorporated before final assessor submission.