Roadmap and critical path

flowchart LR
  P01["P01 Foundation"] --> P02["P02 Requirements"]
  P01 --> P03["P03 Data & storage"]
  P02 --> P04["P04 Responsive shell"]
  P03 --> P05["P05 Goal CRUD"]
  P04 --> P05
  P05 --> P06["P06 Task CRUD"]
  P06 --> P07["P07 Dashboard"]
  P06 --> P08["P08 Search/filter"]
  P03 --> P09["P09 Backup/recovery"]
  P06 --> P09
  P07 --> P10["P10 Accessibility & states"]
  P08 --> P10
  P09 --> P10
  P10 --> P11["P11 Automated tests"]
  P11 --> P12["P12 Responsive pass"]
  P12 --> P13["P13 Browser/device pass"]
  P13 --> P14["P14 Evidence package"]
  classDef critical fill:#6257d9,color:#fff,stroke:#4c43b8,stroke-width:2px;
  class P01,P02,P03,P04,P05,P06,P07,P10,P11,P12,P13,P14 critical;

Critical path: P01 → P02/P03 → P04 → P05 → P06 → P07 → P10 → P11 → P12 → P13 → P14. P08 and P09 were parallel branches converging at P10.

Milestone Exit checkpoint Result
M1 Planned Requirements, backlog and dependencies recorded Complete
M2 Foundation App shell, model and storage adapter working Complete
M3 MVP Goal/task CRUD persists through reload Complete
M4 Feature complete Dashboard, filters, backup and errors complete Complete
M5 Test complete Automated browser/viewports green; Edge/devices recorded Partially complete: manual rows pending
M6 Evidence complete Word/PDF packs rendered and records linked Complete, pending appendix replacements

The manual sessions remain a release checkpoint for the final assessor copy, even though the application and automated evidence package are complete.